Summary
Eleven active sinkhole projects prompted another $462,550 change order, pushing the Scott & Ritter contract to $1.642 million total. Last year's flooding alone caused over a million dollars of sinkhole damage, and the geologist expects more requests soon.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Sep 1, 2026.
Impact analysis
$462,550 added, for a total project cost of $1,642,550.
Homeowners and neighborhoods sitting over karst terrain, plus parks users whose soccer fields needed repairs.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bowling Green
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.